Alatas Service | Field Service |
Location | Hong Kong |
Crane Type | Gantry 30t |
Working with GH Industrias Mecánicas and Dragages Bouygues JV, Alatas Hong Kong the installation of a 30t gantry crane at the MTR XRL820 site. The Alatas team drew up a concise plan that was executed without any problems. The job just took 11 days, well ahead of the target completion date.
The gantry crane will be used to deliver tunnel linings and other equipment into the shaft 24 hours a day / seven days a week. This site is also the launch site for the Tunnel Boring Machine.
Alatas engineers completed the project with the successful load testing of the crane using our water bag system. Alatas Hong Kong will also provide the full range of regular and emergency maintenance and repair services to the owners of the crane.
Job Gallery for Installation of 30t Gantry Crane
Fitting handrails Assembling the gantry Installing trolley