Removal of interior and exterior slewring
bolts |
 |
Hoisting winch wire ropes removed |
 |
Boom cylinders disconnected from boom |
 |
Slip ring wire removed |
 |
Prepare crane for floating cranes arrival |
 |
Lifted boom to hatch cover and secured |
 |
Inspection of new slew bearings |
 |
Transfer of slew bearings, bolt and nuts to floating
barge |
 |
Lifting of crane slew column to remove of slew
bearings |
 |
Clean crane base and slew bearings, fitted bolts
nuts and washers |
 |
Torque bolts to correct settings |
 |
Prepare slew column foundation to install back
crane |
 |
Transfer new bolts and washers inside column |
 |
Lifted crane and installed to the slew column |
 |
Inside bolts fitted and torqued with hydraulic
wrench |
 |
All accessory items reconnected |
 |
Backlash of slew gear pinion checked and adjusted |
 |
Slewing bearing greased prior to function testing |
 |
Function test of crane carried out |