Alatas Americas was contracted to remove an NMF crane tower and pedestal to facilitate the loading of oversized cargo (cold storage boxes). Due to the size of the “cold boxes” the overhang of the NMF aft crane hindered in the loading of the cargo.
The NMF crane and pedestal removal was carried out in the Port of Houston, with the reinstallation to be carried out approximately 60 days later. All work was to be carried out as per NMF crane manufacturer’s standards and by GL certification and overload testing verification.
|
|
|
|
|
|
NMF crane prior to removal
|
NMF crane scaffolding setup |
Adverse weather conditions in Houston |
|
|
|
| |
|
|
|
|
|
|
NMF crane removal |
NMF crane removal |
|
|
|
| |
|
|
|
|
|
|
NMF crane removal preparations
|
NMF crane removal |
|
|
|
| |
|
|
|
|
|
NMF crane removal |
|
Pedestal cutline marked and removed shoreside |
|
|
|
| |
|
|
|
|
|
Pedestal cutline marked and removed shoreside |
NMF crane removed to allow coldbox to be carried |
NMF crane removed to allow coldbox to be carried |
|
|
|
| |
|
|
| |
|
|
| NMF crane replacement gallery |
|
|
| |
|
|
|
|
|
Pedestal edge preparation work |
Pedestal edge preparation work |
Boom and pinions brass sleeves preparation |
|
|
|
| |
|
|
|
|
|
Boom and pinions brass sleeves preparation |
Pedestal and boom transported to vessel |
Pedestal and boom transported to vessel |
|
|
|
| |
|
|
|
|
|
Pedestal and boom transported to vessel |
NMF crane pedestal lifted onboard |
NMF crane pedestal welded into place |
|
|
|
| |
|
|
|
|
|
Pedestal welded into place as per NMF procedures and inspected by GL Surveyor |
Pedestal welded into place as per NMF procedures and inspected by GL Surveyor |
Pedestal welded into place as per NMF procedures and inspected by GL Surveyor |
|
|
|
| |
|
|
|
|
|
Ultrasonic testing carried out on welded
seam as per GL Surveyors request |
NMF crane moved inside hold as vessel had to move to different berth |
Scaffolding constructed to provide working
platform around pedestal slew bearing
mounting machined surface |
|
|
|
| |
|
|
|
|
|
After pedestal was welded, laser
flatness
check carried out on pedestal
slew bearing mounting surface |
After pedestal was welded, laser
flatness
check carried out on pedestal
slew bearing mounting surface |
After pedestal was welded, laser
flatness
check carried out on pedestal
slew bearing mounting surface |
|
|
|
| |
|
|
|
|
|
NMF crane lifted from hold
and refitted onto pedestal
|
New slew bearing bolts installed and
torqued to manufacturers standards |
New slew bearing bolts installed and
torqued to manufacturers standards |
|
|
|
| |
|
|
|
|
|
NMF crane electrics refitted through
pedestal onto electrical connection
posts and slipring reconnected |
NMF crane electrics refitted through
pedestal onto electrical connection
posts and slipring reconnected |
NMF crane wire ropes refitted |
|
|
|
| |
|
|
|
|
|
NMF crane wire ropes refitted
|
NMF crane overload lifting and
functional
tests carried out as per
attending GL
surveys instructions |
NMF crane overload lifting and
functional
tests carried out as per
attending GL
surveys instructions. |
|
|
|
| |
|
|